We are pleased to announce the start of our external decoration programme, which will help protect our homes and improve the appearance of the neighbourhood.
Works will be carried out across a number of streets between October 2026 and April 2027.
|
Programme Dates |
Location |
Properties Included |
|
5 October to 30 October 2026 |
Ferguslie Park Avenue |
Nos. 53 to 79; Nos. 81, 83 and 85 |
|
2 November to 27 November 2026 |
Ferguslie Park Avenue |
Nos. 80 to 86; Nos. 88 to 94; Nos. 96 to 134 |
|
30 November to 11 December 2026 |
Kirklea Gardens |
Nos. 1 to 23; 6 to 8 Kirklea Gardens |
|
14 December 2026 to 8 January 2027 |
Blackstoun Road / Killoch Avenue / Oakridge Crescent |
93A -103 & 112-118 Blackstoun Road; 1A-1H Killoch Avenue; 129 Oakridge Crescent |
|
11 January to 29 January 2027 |
Darkwood Crescent & Bankfoot Road |
2-18B, 27A-27D, 45A-45D Darkwood Crescent; 29A-39C Bankfoot Road |
|
1 February to 19 February 2027 |
Candren Road & Calder Road |
26A-145B, 38A-40B, 42A-44B Candren Road; 1A Calder Road |
|
22 February to 12 March 2027 |
Dalskeith Avenue |
Nos. 1 to 40, 42 and 44 |
|
15 March to 2 April 2027 |
Dalskeith Crescent |
Nos. 2 to 84 Dalskeith Crescent |
All tenants residing at the affected properties will be notified of the works in advance.
Please note:
· All dates are subject to suitable weather conditions.
· Residents will be updated if there are any significant programme changes.
· Access may occasionally be required to complete works safely and efficiently.